Part 39: Acquisition of Information and Communication Technology

Status: Proposed rule published. Last verified against acquisition.gov on November 22, 2026.

All FAR parts

What it covers

Covers buying information and communication technology.

What the overhaul would change

The proposed rule rescopes the part around information and communication technology, removes a privacy section and the Privacy or Security Safeguards clause, adds the NICE cybersecurity workforce framework, and directs planners to consult federal guidance on positioning, navigation and timing services.

Sources: Proposed rule preamble, Federal Register, June 23, 2026. Summary written November 21, 2026.

Model deviation text
Issued June 12, 2025. Read on acquisition.gov
Updates
None listed
Practitioner Album
Open the Practitioner Album
Formal rulemaking
Proposed rule, June 23, 2026 (comments closed July 23, 2026)
Agency deviations
32 listed on acquisition.gov

Agency deviations for Part 39

As listed on acquisition.gov. Each link opens the agency's deviation document.

Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 1, 2, 4, 33, 39, 40, and 53

Proposed rule. Published June 23, 2026. Covers FAR parts 1, 2, 4, 33, 39, 40, 52, 53.

Summary and dates · Federal Register

Part 38 · Part 40 · All parts

Need to know what a rule means for you?

Three Rivers Solutions helps contractors and associations read, comment on and plan for procurement policy changes.

Discuss a project

Get the weekly note

A short note each Friday on what the federal contracting numbers show. Free; unsubscribe any time.

Sources: Acquisition.gov, FAR Part 39, FAR part and deviation guide. Titles, summaries and dates are shown exactly as published. Page refreshed November 22, 2026.

This tracker is for information only and is not legal advice. Always rely on the official published text.